Beeton Creek Sanitary Forcemain Replacement and Bridge Removal

Project No. T19-05

Notice for Start of Construction

Please be advised that the Town of New Tecumseth has recently awarded the Beeton Creek Sanitary Forcemain Replacement and Bridge Removal construction contract. The project has been awarded to Avertex Utility Solutions Inc. 

The scope of the work for this project includes removal and replacement of the Sanitary Forcemain approximately 150m north and south of the Beeton Creek as well as removal of existing C.N.R. Bridge.

The Contractor started construction activities on August 12, 2019. The works were anticipated to be substantially completed by October 15. However, due to weather and unforseen aspects of the work, the work is now anticipated to be completed and the trail reopened at the end of October, 2019. We apologize for any inconvenience this may cause to any trail users. 

During the construction period the existing Trail will be closed to the Public between Lilly St. and the 10th Line. 

Should you have any questions or concerns related to this project, please do not hesitate to contact:

 

Project Contract Administrator

Ms. Kim Sayers R.V. Anderson Associates Limited

2001 Sheppard Ave.East

Suite 300

Toronto, ON, M2J 4Z8 Tel: (416) 497-8600 x 1240

Town of New Tecumseth

Mr. Kim McDonald Contract and Construction Administrator

Engineering Department

Town of New Tecumseth

10 Wellington Street East Alliston, ON, L9R 1A1 Tel: (705) 435-3900 x 1258