Dillane St E and Keogh St Reconstruction

Contract No. T25-02

The Town of New Tecumseth has hired Trisan Construction to reconstruct Dillane Street East and Keogh Street. Triton Engineering Services will help oversee the project. The work includes earth excavation, storm and sanitary sewer replacement and rehabilitation, new asphalt, adding concrete curbs and sidewalks, putting up streetlights, and more.

Because of this, the roads will be closed to through traffic from May 5 - August 15. Local and emergency access will still be available. Signs will be put up before construction starts, and detour routes will be marked to help drivers and pedestrians get around the closure.

Community Impact

Residents can expect some delays and inconveniences during this period. The Town respectfully asks for cooperation and patience to ensure the project is completed in a timely and efficient manner.

Road Closure and Detour Plan

 A picture of a map of Tottenham Showing the road closures

Project Updates and Notices

Project updates and notices will be provided on a regular basis to ensure residents and stakeholders stay informed of the progress of the Works. 

August 27, 2025 - Notice of Project Update

August 14, 2025 - Notice of Project Update

July 3, 2025 - Notice of Water Shut-off - Fire Hydrant Replacement

July 2, 2025 - Notice of Water Shut-off - Watermain Valve Replacement

June 24, 2025 - Notice of Watermain Replacement - Dillane St. E.

June 23, 2025 - Notice of Watermain Replacement - Dillane St. E.

May 7, 2025 - Notice of Night Construction 

April 23, 2025 - Notice of Construction and Temporary Road Closure

February 12, 2025 - Advance Notice of Construction and Temporary Road Closure

Frequently Asked Questions

 

What are the construction Work hours?

Work will take place between 7:00 a.m. to 7:00 p.m., Monday to Friday. In the event of extreme or emergency situations, work may take place after hours and/or on weekends and only with the Town’s approval, however not anticipated.

What kind of inconveniences are expected during construction?

You may experience dust, noise and other inconveniences. Every effort will be made to reduce and mitigate the impacts.

Additionally, driveway access may be disrupted from time to time. As required, on-site personnel will coordinate driveway disruptions/closures with residents to minimize the length of closure and to ensure alternate parking arrangements are made. Residents that require special accommodations that could be adversely affected by driveway access interruptions are asked to contact the Town Project Manager identified within this Notice as soon as possible.

Will our general garbage, yard waste and recycling services be disrupted during construction? 

Please have your waste and recycling bins out at the end of your driveway prior to 7:00 a.m. on your regularly scheduled pick-up day. The Contractor will relocate the bins as necessary to enable the County of Simcoe’s solid waste contractors to gain access to them. We ask that you label your municipal address on all bins to assist us in returning them. 

Will our mail delivery be disrupted during construction?

Mail delivery will continue throughout construction and the Contractor will coordinate any required temporary mailbox relocations with Canada Post. If mailbox relocations are required, further notice will be provided to residents. 

What impacts will there be with the Tottenham Public School and pedestrian access?

Vehicle access to the Tottenham Public School will be maintained from Rogers Road southerly to Queen Street South. A pedestrian detour will be set up from Mill Street East to the school via The Boulevard and trail to encourage pedestrians to utilize an alternate route. The Contractor is required to have staff stationed at key areas within the construction zone to assist with pedestrians travelling to and from the school during the hour before and after school. 

What impacts will there be to Keogh Park?

The fields and facilities will be available for use during the road reconstruction project. We are committed to working with user groups to ensure safe and accessible use of Keogh Park. During construction, users will be encouraged to access the park from the entrance on Mill Street. For more information on events and permit inquiries, or usage of Keogh Park, please contact the Recreation, Facilities & Culture Department at 705-435-3900 or recreation@newtecumseth.ca

What impacts will there be with on-street parking?

On-street parking will not be permitted within the limits of the road closure in order to allow the Contractor full access to complete the work in a timely manner. Alternative parking locations are available at the public parking (Green P) lot immediately west of First Station No. 3, as well as along Mill Street East. Please obey the posted signage onsite, as well as the Town Parking and Traffic By-Law at all times. 

Will the school bus services be disrupted during construction? 

Work is planned to take place during the school year. The bus consortium has been consulted and will be utilizing Rogers Road South to Queen Street South. Bussing to and from the YMCA daycare will be maintained throughout the duration of this project.

Will my utilities be disrupted during construction? 

Telephone, electrical, cable TV, and gas services should not be affected by the construction, barring any unforeseen circumstances.

Who do I call if I have a problem with the Construction activities?

For an immediate response, please contact the Town’s Project Manager or the Project Consultant Representative identified within this Notice.

Will any trees be cut during this construction?

Locations have been identified throughout the project and impacted property owners will be notified in advance of the work.

 

 Other Important Information

 

Building Pre-Construction Survey

Prior to the start of construction, the Contractor will also be carrying out a pre-construction survey of the project area. This is to provide a record in the unlikely event that any damage occurs as a result of the construction activities. The survey will consist of an inspection of both the interior and exterior of buildings/property to verify existing conditions. A separate notice from OZA will be circulated to schedule these surveys with affected residents. Participation is voluntarily however it is recommended as it is an important measure for determining if any losses are caused by the construction activities.

Restoring Driveways

Per the Town’s engineering standards, contract, and past practices, driveway reinstatement will occur as follows:

  1. Driveway material is to be replaced like for like. For gravel driveways the Town portion of the right-of-way to property line will be paved with asphalt.

  2. All driveway restoration is to be completed to property line with a gradient between a minimum and maximum of 2.0% and 7.0% respectively.

  3. Under certain circumstances where the road elevation has changed it may necessitate grading beyond the property line. In these cases, advance notice is provided to the Owner(s) and a permission to enter/grading agreement is required to carry out the necessary restoration work. Upon completion, a final release form is required from the Owner(s) confirming that they are satisfied with the work completed.

  4. Under certain circumstances where the existing driveway under pre-existing conditions exceeds a 7% gradient, a best effort approach may be taken to match the pre-existing slope or improve upon the gradient by paving to or beyond the property line to achieve the maximum 7% gradient. This is however, reviewed on a case-by-case basis.  

  5. In preparation of paving the driveways, the Contractor and Inspector will review and agree upon the best tie-in point to match existing asphalt prior to saw-cutting the driveway.

 The match points have been identified during detailed design and are part of the Contractor’s scope of work to complete. The limits beyond these match points are not considered part of the scope of this project and included within the contract. At this time, we are not aware if the Contractor is interested in entering into a private agreement with the Owner(s) to pave the remaining balance of the private driveway. In the event the Contractor decides to take on these requests the Town would remain responsible for only the costs associated for the driveway portion as set out in the contract including warranty obligations for said portion. Any private agreements would be solely between the Contractor and Owner(s).  

Privately Owned Items

The Contractor will not be responsible for damages to any privately owned items on Town property. Property owners should remove items located within Town right-of-way such as landscaping and/or decorative objects. If you have a sprinkler system and/or septic bed located in close proximity to the Town property limits, please contact the Town Project Manager or Project Consultant Representative identified within this Notice. 

Safety

Construction involves the use of heavy equipment and the unavoidable creation of obstacles. These circumstances are often attractive to children, and as such, we ask that you please caution your children to stay clear of the construction work zone.

While the contractor is required to conduct the work in a safe manner, we ask that you please take extra caution during the construction period as an additional measure.

Should you have any questions or concerns related to this project, please contact the following project team: 

Project Consultant:

Taylor Kramp, P. Eng.

Project Manager

Triton Engineering Services Limited

71 Broadway, Unit 4

Orangeville, Ontario, L9W 1K4

Office: 519-941-0330 Ext. 224

Email: tkramp@tritoneng.on.ca

Town Project Manager:

Joel John-Ogbe, EIT.

Project Manager, Capital Engineering

Town of New Tecumseth

24 Tupper Street West

Alliston, Ontario, L9R 1H2

Office: 705-415-3045

Email