Please be advised that the Town of New Tecumseth is preparing to undertake road and bridge improvements in 2026 along Church Street North, between Victoria Street and Hussey Street in Alliston.
The primary scope and objectives of the project are to:
- Urbanize the road cross-section, eliminate roadside ditches and ensure the proper conveyance of stormwater flows
- Improve the condition of existing infrastructure (watermain, sanitary sewer)
- Replace and widen the bridge
- Improve traffic operations on Church Street North
- Install bike lanes
- Merlyn Duffin Walkway extension along the Boyne River
The Town welcomes your input on this project. Community members interested in the proposed improvements are encouraged to review the project materials and the Virtual Public Open House (VPOH) presentation below, and to share feedback accordingly. If you have questions, comments, or wish to be added to the Project Contact List for future updates, please complete the questionnaire and contact the project team members listed below. Please submit any questions related to the VPOH by January 23rd. The typical comment period has been extended to account for the holiday season.
Tatham Engineering Limited, Project Engineer
Mrs. Emma Wilkinson, H.B.A., B.E.Sc. P.Eng.
Project Manager, Senior Engineer
Tel: 705-444-2565 ext. 201
Email: EWilkinson@tathameng.com
Town of New Tecumseth
Rob Greenwood, PMP, C. Tech
Project Manager, Town of New Tecumseth
Tel: 705-415-1930
Email: rgreenwood@newtecumseth.ca
Project Location Key Map

| Project Materials |
|
|
| Frequently Asked Questions |
|
| What are the construction work hours? |
|
Work will take place between 7:00 a.m. and 7:00 p.m., Monday to Friday. In the event of extreme or emergency situations, work may take place after hours and/or on weekends and only with the Town’s approval, however not anticipated.
|
| What kind of inconveniences are expected during construction? |
|
You may experience dust, noise and other inconveniences. Every effort will be made to reduce and mitigate the impacts.
Additionally, driveway access may be disrupted from time to time. As required, personnel on-site will coordinate any driveway disruptions/closures with residents to minimize the length of closure and to ensure alternate parking arrangements are made.
Residents that require special accommodations that could be adversely affected by driveway access interruptions are asked to contact any of the Project Representatives identified at the end of this presentation as soon as possible.
|
| Will our general garbage, yard waste and recycling service be disrupted during construction? |
|
Waste collection services will be maintained during construction. Please have your waste and recycle bins out at the end of your driveway prior to 7:00 a.m. on your regularly scheduled pick-up day. If necessary, the Contractor will relocate the bins to enable the County’s solid waste contractors to gain access to them. We ask that you label your municipal address on all bins to assist us in returning them.
|
| Will our mail delivery be disrupted during construction? |
|
Mail delivery will continue throughout construction and the Contractor will coordinate any required mailbox relocations with Canada post. If mailbox relocations are required, further notice will be provided to residents.
|
| Will the school bus services or school cross walks be disrupted during construction? |
|
School bus arrangements will be coordinated with the County’s School Bus Consortium. Adjustments to the route or pick-up/drop-off locations may be required due to the construction. Adjustments to the school cross walk locations may also be required when construction is in proximity to the existing crossings. If any adjustments are required, further notice will be provided to affected residents.
|
| Will my utilities be disrupted during construction? |
|
Telephone, electrical, cable TV and gas services should not be affected by the construction, barring any unforeseen circumstances.
|
| Who do I call if I have a problem with the Construction activities? |
|
For an immediate response, please contact the Town’s Project manager or the Consultant Representative identified within the Project notice that will be provided at the commencement of Construction.
|
|
| Project Updates and Notices |
|
March 26, 2026
The project team is currently finalizing responses to feedback received through the Virtual Public Open House (VPOH). These responses are anticipated to be distributed later next week and will also be posted on this project webpage once available.
We encourage anyone with outstanding questions, concerns, or additional feedback to follow up directly with a member of the Project Team.
Thank you to everyone who has taken the time to participate and provide input to date—your engagement is greatly appreciated.
In addition, Alectra continues to be onsite completing tree trimming activities and relocating existing hydro poles. Alectra’s work is expected to continue through May 2026. An updated overall project schedule will be shared alongside the VPOH feedback.
|
| Project Progress and Construction Photos (To be Updated During Construction) |
| |