2023 Road Reconstruction Extension
2023 Road Resurfacing Project - 10th Sideroad is Deferred until June of 2024.
The extension is necessary due to additional time required due to the following reasons:
• Additional concrete works required in Tottenham & Beeton Areas
• Delays in obtaining Utility locates
• Weather related delays
• Delayed tendering & award of Contract. Contract was not executed until July 24, 2023.
• To better coordinate with the Line 6 / Sideroad 10 Signalization project
Work has been halted until spring of 2024 when better weather arrives.